SOP for Operation of the Muffle Furnace

OBJECTIVE
To lay down a procedure for the Operation of the Muffle Furnace.

SCOPE
This procedure is applicable for Muffle Furnace installed in Quality Control Department, at PharmaInfo Limited.

RESPONSIBILITY
Execution: Chemist and above – QC department.
Checking: Asst. Manager and above – QC department


PROCEDURE
  • Switch on the furnace.
  • The furnace temperature is pre-set using the temperature controller cum indicator as follows.
  • Press the red switch and rotate the black knob till the desired temperature is indicated in the digital display.
  • Release the red switch. The digital display will show the present furnace temperature.
  • Allow the furnace to stabilize at the set temperature for some time.
  • Put off the furnace and then open the door and introduce the sample.
  • Close the door properly and switch on the furnace again.
  • Switch off the furnace while loading or unloading

REFERENCE
Nil

ABBREVIATION
SOP: Standard Operating Procedure
Q.C: Quality control

ANNEXURE
Nil

REVISION HISTORY
Nil