OBJECTIVE
To lay down the procedure for the Operation and Calibration of the Conductivity Meter for better and error-free use.
SCOPE
This procedure applies to the Conductivity Meter, installed in the Quality Control department at Pharmainfo Limited
RESPONSIBILITY
Chemist and above - QC department.
Checking: Asst. Manager and above - QC department.
PROCEDURE
Operational Procedure
- Switch on the mains.
- Switch on the ‘POWER’.
- The display shows ‘count in μs/cm ’.
- Rinse with distilled water and dry it with tissue paper.
- Ensure that before using the conductivity meter, it should be calibrated.
- Immerse both probes in the solution to be measured.
- After a while, the unit will display the temperature and conductivity of the solution in micro siemens/millisiemens units.
- On completion remove the conductivity cell and temperature probe from the test solution.
- Rinse the conductivity cell and temperature probe with distilled water and dry it with tissue paper.
- Keep the cell immersed in distilled water in between and after the measurement.
- Switch “OFF” the mains.
Calibration Procedure
Frequency: Daily
- Rinse the conductivity cell and temperature probe with distilled water and dry it with tissue paper.
- Dip the conductivity cell in 0.001 M Std. KCl solution
- Check the standard conductivity switch is in an upward position so that the full range of display is read.
- Record the observation in Annexure-1 and if necessary turn the ‘standardize’ shaft with a screwdriver to get the correct conductance of the solution.
REFERENCE
Nil
ANNEXURE
Annexure No. - 1: Calibration report of conductivity meter
ABBREVIATION
SOP: Standard Operating Procedure
Q.A: Quality Assurance
No. : Number
Q.C: Quality control
hr: Hour
KCl: Potassium Chloride
Std. : Standard