Objective
To lay down a procedure for the operation of metal detectors and vertical deduster.

Scope
This procedure is applicable to the operation of metal detectors and vertical dedusters in the production area.

Responsibility
Officer to implement this procedure 
Department Head responsible for overall compliance with this procedure
Procedure
Machine setting
  • Ensure cleanliness of the area and equipment. Take line clearance from the QA person. Affix the ‘UNDER PROCESS’ label duly filled and signed on the equipment and record all the observations in the equipment usage log sheet as per the given SOP.
  • Adjust the height of the vertical deduster such that its inlet chute positions slightly below the outlet chute of the compression machine by unlocking the locking knob and then lifting up / down the machine body and finally locking the locking knob.
  • Adjust the height of the metal detector by unlocking the locking knob.
  • Adjust the position of the metal detector coil by loosening the knob and then set the final position of the coil such that the metal detector’s inlet chute positions slightly below the outlet chute of the tablet de-dusting vertical deduster finally tighten the knob.


Operation
  • Turn ‘ON’ the compressed air supply to the vertical deduster.
  • Turn ‘ON’ the ON/OFF knob of the metal detector. A metal detector will turn ON.
  • Enter the password. Fill in the product detail such as product name, and batch no. and save it.
  • Deduster will start. Feed some tablets in the inlet chute of the de-duster. Set power and frequency such that tablets move upward without getting streaked.
  • Once every parameter is set. Operate the compression machine as per respective SOP.
  • On completion of the operation, disable the deduster and turn ‘OFF’ the ‘ON/OFF’ knob of the metal detector.
  • Affix the ‘TO BE CLEANED’ label duly filled and signed on the machine and record all the observations in the equipment usage log sheet as per the given SOP.

ABBREVIATION:
QA: Quality Assurance
SOP: Standard Operating Procedure
RHS: Right-Hand Side
LHS: Left-Hand Side

ANNEXURE
Nil

REVISION HISTORY
Nil