OBJECTIVE
To lay down the procedure for breakdown maintenance.
SCOPE
This SOP shall be applicable for equipment, machinery and facility breakdown.
RESPONSIBILITY
Operator
Technician
Officer
Executive
ACCOUNTABILITY
Head of Engineering
PROCEDURE
- Communicate the breakdown to the engineering department and hand over the breakdown intimation note.
- Officer/executive - engineering will depute the technician to attend the breakdown.
- While carrying out the breakdown maintenance, ensure that the following steps are taken:
- Switch off the power supply of the machine and put a board on the machine stating “UNDER MAINTENANCE”.
- Discuss the incidence of breakdown with the operator to understand the details.
- Carefully inspect the machine and check the cause of the breakdown.
- After identifying the cause, if any parts/ assemblies of the machine are to be dismantled, mark them properly for identification.
- Keep the dismantled parts of the machine in the proper tray and clean them thoroughly.
- After the repairs, assemble the parts, check the assemblies for smooth operations and then assemble them on the machine.
- Lubricate the parts wherever lubrication is required, as per the lubricant recommended by the machine manufacturer/ supplier.
- After satisfactory repairs of the breakdown, show the performance trial to the concerned person and get it confirmed in the breakdown intimation note.
- Remove the “UNDER MAINTENANCE” board.
- Record this information in the machine history card.
- In case of any major part is to be replaced, which may affect the machine's performance should take place through a change control procedure.
- Maintenance work required other than the breakdown of process-related equipment/instruments shall be communicated through maintenance requisition.
ABBREVIATION
SOP: Standard Operating Procedure
ANNEXURE
Nil
REVISION HISTORY
Nil
0 Comments