SOP for Logbook Preparation

PURPOSE
To lay down a procedure for preparing the log book for equipment.

SCOPE
This procedure applies to all equipment situated in PharmaInfo Ltd.

RESPONSIBILITY
Officer Production / Officer QA

ACCOUNTABILITY
Head Production / Head QA

PROCEDURE
  • All the equipment must have an individual logbook. 
  • All the activity done on equipment shall be recorded in the logbook.
  • The logbook contains operational, cleaning, and breakdown/maintenance records.
  • The logbook for any equipment shall contain the following parameters:



  1. Equipment Name
  2. Equipment Identification Number.
  3. Department
  4. Location
  5. Date
  6. Name of the product
  7. Batch Number
  8. Mfg. date
  9. Exp. Date
  10. Batch Size
  11. Operational activity (Procedure time)
  12. Done by
  13. Checked By
  14. Verified By
  15. Remarks
  • The log shall be prepared in a register form as per Annexure-I.
  • Any equipment breakdown must be recorded.
  • The log book for breakdown contains the following parameters:
  1. Date
  2. Details of breakdown
  3. Corrective action taken
  4. Rectified by
  5. Checked by
  6. Remarks
  • The logbook shall be in a register form as per Annexure II.
  • Maintain the records of all equipment as per the log book.


ANNEXURES
Annexure I: EQUIPMENT LOG BOOK
Annexure II: BREAK DOWN LOG BOOK

ABBREVIATIONS
SOP: Standard Operating Procedure
QA: Quality Assurance

REVISION HISTORY
Nil